Completed

Ahmedzai Perennial & Flood Irrigation, Sub Project, Zhob

Project Description

The Ahmedzai sub-project comprises (i) main diversion weir across the stream Sawar Rud-a tributary of Zhob River; (ii) perennial irrigation scheme along right bank and (iii) the flood irrigation scheme along left bank. The Perennial Irrigation Scheme (PIS) supplies water round the year whereas the Flood Irrigation Scheme (FIS) supplies water to the agricultural land only during floods when there is availability of surplus flows in the stream. Right and left bank command areas of Ahmedzai sub-project will receive irrigation water from perennial and flood flows respectively. The design of interventions related to all components of this subproject. These are divided as, (i) Irrigation Network – Rehabilitation and Lining. (ii) Flood Protection. and (iii) Weir construction. The scope of work for the subproject include remodeling of the existing Ahmadzai weir along with the rehabilitation and partial lining of perennial and flood channels and associated structures.

Salient Features

S.NO
01 Total Cost 669.700 (Rs. Million)
02 Contract Closed 650.241 (Rs. Million)
03 Total Command Area 859 hector
04 Ahmadzai Weir New Construction
05 Perennial Canal Length 3220 Meter
06 Flood Channels Length 3500 Meter
Project Progress
Physical Progress 100%
Financial Progress 100%
  • Contractor Noor ul haq & Brothers
  • Commencement 14th Dec 2020
  • Completion Date 18th March 2024

On-site Visual Documentation