In Progress
Churri Infiltration Gallery Sub Project Khuzdar
Project Description
The Churri Infiltration Gallery Subproject is designed to enhance irrigation efficiency and ensure sustainable water use. It consists of three core components: (1) an Infiltration Gallery constructed to capture and divert subsurface water, (2) Perennial Channels developed to transport and distribute water reliably to agricultural fields, and (3) a Protection Bund built to protect the system and nearby land from floods, erosion, and other natural hazards. Together, these structures improve water availability, agricultural productivity, and community resilience.
Salient Features
| S.NO | |||
|---|---|---|---|
| 01 | Length of Infiltration Gallery | 270 m | |
| 02 | Length of Main Canal | 4000 m | |
| 03 | Length of Branch Canal | 7150 m | |
| 04 | Command Area | 800 hectare |
Project Progress
Physical Progress
15%
Financial Progress
15%
- Contractor M/s Haji Abdul Hameed Bangulzai
- Commencement 26th Dec 2024
- Completion Date N/A
On-site Visual Documentation