Karkh valley development subproject
consists of three parts: (a) general works – which relate to the Karkh Valley
as a whole, (b) weir construction at Jhalaro, and (c) weir rehabilitation at
Chutta. Construction of this project will strengthen the existing irrigation
system, ensuring availability of water for both cropping seasons. The proposed
the intervention for the subproject include; (a) guide bund / flood protection
works, (b) construction of new Jhalaro weir, (c) weir rehabilitation at Chutta,
(d) Rehabilitation of Chutta lift irrigation (pump house), and (e) lining of
unlined existing channels.
SALIENT
FEATURES:
|
Total Cost |
1095.932 (Rs. Million) |
|
Total Command Area |
2535 hector |
|
Jhalaro Weir |
Rehabilitation & Upgradation |
|
Chutta Weir |
Rehabilitation & Upgradation |
|
Minor Channels |
Total Length 19,773 |
|
Flood Protection Bund (08 Nos.) |
Total Length 5,186 Meter |
PROJECT PROGRESS:
Completed