The
proposed the intervention for the subproject include; (a) Construction of two
infiltration galleries, (b) Construction and rehabilitation of water conveyance
system and associated structures, (c) flood protection works for irrigation
canals, construction of project support
facility building at khuzdar city and command area development works. The
sub-project is aimed to rehabilitate and improve damaged infrastructure to
enhance size of command area having irrigation facility.
SALIENT
FEATURES:
|
Total Cost |
1091.806 (Rs. Million) |
|
Total Command Area |
1144 hector |
|
Infiltration Gallery |
Total Length 1310 Meter |
|
Conduit Length |
Total Length 2983 Meter |
|
Canals Length |
Total Length 42,231 Meter |
|
Flood Protection Bund (04 Nos.) |
Total Length 7153 Meter |
PROJECT PROGRESS:
Completed